2-20 INSTALL COMBUSTOR SECTION (Continued)
2-20
12.
13.
14.
15.
16.
17.
18.
19.
Install start bypass valve (Task 2-11).
Install check valve assembly (Task 2-49).
Install igniter plug (Task 2-79).
Install start fuel nozzle holder (Task
2-27) .
Install thermocouple (15). Torque to
100 inch-pounds.
Secure clamps (16) with bolts (17) and
nuts (18),
Secure clamps (19, 20, 21) and spacer
(22) with bolt (23) and washer (24).
Install fuel manifold assembly (Task
2-62) .
INSPECT
FOLLOW-ON MAINTENANCE
Leak Check During Operation
END OF TASK