TM 1-2840-252-23-2
4-32
INSTALL THIRD TURBINE NOZZLE AND SUPPORT (AVIM) (Continued)
4-32
6. Check radial clearance between aft three seals (15)
of third turbine nozzle (7) and shaft (16).
Use thickness gage Clearance shall not be less than
0.005 inch or more than 0.027 inch If necessary,
remove third turbine nozzle and support (5), and file
seals (15) with half-round tile to obtain clearance
Repeat steps 5 and 6.
INSPECT
FOLLOW-ON MAINTENANCE:
Install Combustion Section and Power Turbine (Task 3-
Service Engine Oil System (Task 1-68).
END OF TASK