INSPECT THIRD TURBINE NOZZLE AND SUPPORT (AVIM) (Continued)
4-29
h
Inspect four seals (23) as follows: There shall be
no circumferential cracks (24).
2
Inspect aft side of third turbine nozzle (1) as
follows:
a
Inspect outer shroud (25). There shall be no
more than 10 cracks (26) from vane trailing edges
(27) These cracks (26) must not be longer than 1/8
inch.